Somehow we haven't been to our house since last Wednesday! And I was one of those who stalked the construction site. I think I got over all the anxiety, excitement and restlessness.
We had a meeting with our PM today morning (we have fallen into this ritual of weekly walkthrus with our PM:-) ) and saw lot of changes....
- Trim (baseboards, columns, crown, door casings etc etc) almost done.
- We have tile in masterbath, guest bath and powder room floor (all covered up - I was itching to take a peek, but I was good)
- Metal balusters are installed and all covered up for paint.
- And lot of changes on the outside - we have drive way and lead walk poured.
 |
Drive and lead walk poured |
 |
Columns are in! |
 |
Balusters installed and covered up! |
 |
Glass detailing over study door |
 |
Chair rail and trim in dinning |
 |
Tile in master bath |
 |
Tile in powder room |
 |
Chair rail in foyer |
 |
Hubby measuring to make sure the fridge will fit! |
We walk around with our PM he answered some questions we had and told us about things that will be happening next:
- Side walked will be poured today
- They plan to start final coat of paint today, which may take about 3 days
- Monday they'll work on trimming out electrical, plumbing, etc...
- They plan to do the first clean-up to prepare for flooring after paint
- Hardwood may arrive next Tuesday (it may take 2 days)
- Carpet many come in on Wednesday
- Plumbers were working the bathroom, getting ready for tile in shower and tub
- Tile in shower and around tub in the master has been delayed a little bit, it may go in a day or two (I'm not sure)
- The missing kitchen cabinet has been ordered. Glass door cabinet has been order for butlers pantry (this is not a standard, but we were promised one so they decided to order one for us! )
We also marked the deck and stairs placing today with our PM. So overall, there's a lot going on and I'm unable to keep up with it!:-) We are very happy that our PM is confident that we are in a good shape for closing on September 6th! YAY!!!
The house is looking great!
ReplyDeleteBeautiful home wow they have really done a lot its so pretty!
ReplyDeleteIt all looks great, your bathroom layout is just like ours. I love how elegant the brick looks on the front.
ReplyDeleteThe trim work and detail looks awesome! I love the look of your elevation as well. It all looks fantastic! Congrats!
ReplyDelete